Deciding to buy a home is an enormous and life changing decision.
This guide is designed to give you an idea of the processes involved
and will vary slightly from builder to builder. |
|
Once you have
established a budget & obtained a written preapproval from your lender
you are ready to go |
|
Select your House & Land
Package
|
|
This will consist of 2
separate contracts - one for the land and one for the house, which go
together to form a package. |
|
TIMING |
ITEM |
CLIENT REQUIREMENTS |
|
Week 1 |
Builder to
prepare formal quotation
(some will
charge a fee which is included in quoted price) |
Request Quotation |
|
Week 2 |
Pay deposit on land and sign a contract - see
Land Buyers Purchase Procedure
Guide |
Pay 0.25% deposit on land & sign contract. Make
appointment with your Legal Representative for Land purchase |
|
Week 2 -3 |
Pay deposit (or balance deposit) to builder and sign
your quotation & pay balance of Land deposit |
Obtain formal loan approval from lender (2-3 weeks) |
|
Week 4 |
Builder proceeds to draw plans for Council & Statutory
Authorities |
|
|
Week 5 - 6 |
Builder has Client sign plans and select colours with
Builders Colour Consultant. Settle Land Purchase. |
Sign Plans, Complete Colour Selection
& settle land purchase |
|
Week 7 - 12 |
Builder lodges plans for Council & Statutory Approvals
and approvals obtained. |
Client to provide proof of ownership of Land to builder |
|
Week 10 - 12 |
Builder prepares Building Agreement for execution by
Client |
Client signs building agreement & provides Authority
from bank to commence construction |
|
Week 13 |
Builder completes final construction plans and places
orders with suppliers |
|
|
Week 14 |
Construction
Starts - 6 - 9 months until completion
(This will
vary with weather conditions & house size) |
|
|
|
Approx Construction Payment Schedule* |
|
|
|
Initial Deposit |
$2,000 - $4,000 |
|
|
|
Balance of deposit |
5% |
|
|
|
Slab Complete |
20% - 25% |
|
|
|
Frame Complete |
25% - 30% |
|
|
|
Brickwork & Roof complete (Lockup) |
20% |
|
|
|
Internal Linings |
15% - 20% |
|
|
|
Completion & Handover |
5% - 10% |
|
|
|
* Varies from builder to builder |
|
|